Estudio Damgo - Week 10

This week the students prepare for a community meeting with the parents and children of Malaunay school. We present the construction progress to date, the design details, and material boards for discussion.  On site, the crew is finishing the concrete walls, the rammed earth wall is poured, and we're prepping for bamboo delivery the following week.  The septic tank is 100% excavated and hollow block walls are being placed to form three chambers. - Photos by Paul Benzi Florendo

Cheyenne Lopez presents the successful fundraising for the project.

 The community of Malaunay attentively listen to the student presentation.

I point out the progress on the septic tank to Larissa Gutsch, the German Fine Arts instructor at FU.  Her students are painting two wall murals for the Estudio Damgo project.

Group photo: FU employee, Jay (foreman), Rick, Rhea, Leigh, Efren, Anna, Von, Al, Daryl, Cheyenne, FU driver (back), and Ray.